Project Description

Solid Oak Doors & Screens

The Scottish Parliament Building 

Edinburgh, UK

CLIENT: Parliament Project Team

CONSTRUCTION MANAGER: Bovis Lend Lease

DESIGN TEAM: RMJM / EBMT

IN NUMBERS

£43m contract value
230 Mivan staff based on-site
Approximately 500,000 man-hours
Over 2 years project duration
More than 6000 MDF panels Installed
600 specialist solid timber doors
The project was completed October 2004

SCOPE OF WORKS: Design and build contract to deliver the interior fit-out of towers 1 to 4, debating chamber, MSP building, Queensferry House, this included:

  • Partitions
  • Bespoke door sets and screens
  • Bespoke committee room desks / furniture
  • Acoustic wall panelling
  • GRG feature ceilings
  • Debating chamber furniture including MSP desk, raised steel flooring, acoustic chambers, press booths and ceiling cladding